Summary: About 8:00 am 02/03/03 ***** personal began to set up the 50-ton rough terrain crane at the oil barge dock to unload cargo for the ***** project. After the crane was positioned approximately 8′ from the edge of the bulkhead and all pre-lift checks had been made with dry run we proceeded to lift...