This summer we saw a 300,000-gallon water tank fail which pushed a generator into a covered process which led to a release of the HHC/EHS. The questions I wish to pose are:
- Should the water tank have fallen under the PSM/RMP program due to its proximity to the covered process?
- Should the proximity of the water tank be part of the facility siting assessment in the PHA?