If we are making a final “tie-in” weld between two segments of pipe that have already been independently pressure tested, that specific weld can be exempt from a final system pressure test if:
It is a butt weld.
It undergoes 100% RT or UT.
It undergoes an in-process examination (visual inspection of fit-up and passes).