Fixed Fire Protection system asphyxiates supervisor

At 1:30 p.m. on August 7, 2022, an employee worked as a production supervisor in his office when the deluge system alarm was activated. Approximately 30 seconds after the audible alarm was engaged, the foam generators were activated and began to disperse 2.2% high expansion foam.  The employee attempted to exit his office to reach

Line Break Gone Wrong… Employee burns hand after disconnecting nuts on pressurized NH3 line

At approximately 9:00 a.m. on March 15, 2022, an employee, 30, disconnected nuts to a line for service and repair work. The employee was working to depressurize lines of ammonia for service work. The team had isolated, performed proper lockout/ tagout, and bled the line assigned for work off. The employee began disconnecting nuts on

Safety Thought of the Week… incubating accidents

This is a great synopsis of how serious accidents build within an organization over time because of the lack of a functioning SMS. When reading this, think “swiss cheese model” from Reason and the “domino model” from Heinrich. Disasters are essentially organized events. To occur, they typically require the systemic and prolonged neglect of varying

Safety Thought of the Week … Disasters are essentially organized events

This is a great synopsis of how serious accidents build within an organization over time because of the lack of a functioning SMS. When reading this, think “swiss cheese model” from Reason and the “domino model” from Heinrich. Disasters are essentially organized events. To occur, they typically require the systemic and prolonged neglect of varying

Flanged joint pressure and tightness testing

When a facility’s hazardous materials piping is assembled with bolted flanged joints, it needs a maintenance procedure to properly assemble and disassemble these flanged joints.  Along with this procedure, a means to pressure/leak test the bolted flanged joint must be used to ensure leak tightness. Subject to code/regulatory requirements, the worker should establish:

Well-written safety programs are foundational to an SMS – not a bureaucracy in safety management

A movement within the safety community, primarily online banter, somehow finds fault with a WRITTEN safety management system (SMS).  There are even books published on the topic that are being pushed, decrying written programs as a bureaucratic waste of time, too controlling, no value added, etc.  I find this very sad, but they do have

ASME PCC-1 offers training guidance for personnel assembling and disassembling flanged joints

A RAGAGEP, which is often overlooked for pipe flanges but is fair game for OSHA and EPA to reference, is ASME PCC-1, Guidelines for Pressure Boundary Bolted Flange Joint Assembly.  The RAGAGEP outlines the training personnel needs to safely assemble and disassemble flanged joints in hazardous material(s) piping circuits.  A facility with flanged piping should

QA/QC for flanged joints

Training and qualified personnel must assemble flanged joints in hazardous materials piping systems (see Appendix A of ASME PCC-1). Consideration should be given to establishing a finished joint examination process as part of the facility’s QA/QC assurance program.  A leak or failure in a piping system can be a minor inconvenience for low-consequence fluids, or